Sysco Food Services of Eastern WI
KBS was awarded this design/build cooler/freezer addition that also included a new office addition and human resources office remodel. Excel Engineering is the engineer for this project. The project was completed in July of 2004.
Address:
One Sysco Drive
Jackson, WI
Challenges:
Final award of this Design/Build project to KBS Construction, Inc. was on December 15, 2003, a three week delay from anticipated. As a result, the Design/Build Team had to move into a fast track mode to complete the Construction Documents and Permitting in an effort to beat the oncoming winter weather. Successful acquisition of an Early Start Permit allowed Site and foundation work to commence in early January; less than four weeks after award.
A two story office addition adjacent to the main office & plant entrance was constructed in very tight quarters. Significant planning and material-equipment staging was necessary so as not to impact the daily operations of the Owner.
The project achieved substantial completion in less than 6 months.
|